The Third Party Inspection for Storage Tank article provides a sample procedure for storage tank inspection and testing in shop and site. You may review storage tank inspection and test plan with this procedure.

This content guides about all necessary stages in the production of the storage Tanks from the examination of material, welding, fabrication, NDE, dimensional inspection to the final inspection, preservation and packing to despatch to site. This content is primarily for mill and prefabrication stages with site erection being covered in outline only.
You need to take this point in account this article is written for a typical storage Tank and might not be complete for special cases.
All storage Tank inspections and tests are carried out against the approved drawings, purchase order specifications, purchasers or company standards, and within the practices and rules of the country, state or province and any government decrees, laws, ordinance or regulation as may apply.
The applicable codes and specifications for the Storage Tank which is under construction process are:
- Design code
- Purchase order specification
- Purchaser’s standards
- Approved drawings
And the applicable codes and standards are:
- API 650
- API 620
The applicable codes and standard may be based other international standards such as BS 2654 and etc. This content is general and can be useful if even the design code is different from API Code.
Required Documents for Third Party Inspector Review:
The list of documents normally is agreed in the Pre Inspection meeting which is hold several weeks before actual commencement of inspection work. The parties which are participated in this meeting are manufacture, purchaser and third party inspection agency representatives.
These are the list of documents which are normally agreed to be presented to the inspector:
- Storage Tank Purchase Order or Contract
- Storage Tank Manufacture Quality Control Plan
- Storage Tank Inspection and test plan
- Storage Tank Data Sheet
- Storage Tank Approved Drawings
- Storage Tank Material Test Reports
- Storage Tank Welding Specification Procedures (WPS) and Procedure Qualification Records(PQR)
- Storage Tank Welding Map
- Storage Tank Welders Qualifications Reports
- Storage Tank NDE procedures i.e RT, UT, MT, PT and PMI
- Storage Tank NDE Personnel qualifications Reports
- Storage Tank Heat treatment procedure
- Calibration Certificates for Test Equipment
- Storage Tank Hydrostatic Testing Procedure and Water Quality Document
- Storage Tank Preparation and Painting Procedure
- Storage Tank Preservation, Packing and Shipping Procedure
- Storage Tank Packing List
Third Party Inspection for Storage Tank – Material Inspection
The first actual inspection work in the storage Tank is raw materials inspection.
The original or authenticated copies of mill test certificates of material normally are available at manufacturer’s premises.
The third party inspector examines these certificates for compliance with specifications and where appropriate, drawings.
The review includes checks on:
- Certificate No.
- Heat or cast No.
- Chemical composition.
- Mechanical properties.
- Heat treated condition.
- NDE applied and results.
- Surface finish
Then the inspector witnesses the materials identification on the certificates against materials marking. It is also necessary to check with storage Tank drawing datasheet, material list and other specification as appropriate.
The identification such as Heat No. needs to be transferred to cut off components.
Visual inspection for surface finish and probable defects are done and dimensional compliance with specification need also to be controlled.
When the third party inspector carried out the material inspection, then provides inspection visit report (IVR), the report contains following items:
- Confirmation of satisfactory document review
- Record of the endorsement of certification reviewed/witnessed
- Record of all non-conformities
- Record of any tests witnessed and the result
Third Party Inspection for Storage Tank- Fabrication Inspection
When the storage tank material inspection carried out and result was satisfactory or non-conformities closed by remedial action, then storage tank manufacture will be authorised to start fabrication.
The inspection scope is determined in ITP, some clients prefer to have stringent control and put the TPI inspector in more “hold points” in fabrication activities and some others may take lesser “hold points” and put TPI much more in the review document.
This depend to the inspection budget which client assign for inspection, much more inspection will have much more costs and less risks and conversely less more inspection will have less costs but more risks.
Third party Inspector is pays attention to the following points on a basis to be outlined in the purchaser’s documentation, quality plan, test and inspection plan, or other document, as notified to the inspector.
Third Party Inspection for Storage Tank- Plate Preparation
Third party inspection carries out visual and dimensional check to ensure compliance with WPS and specification. Where specified, weld bevels are examined by MT or PT after grinding/machining.
Edges and weld bevels need to be clean, dry and free from surface defects, laminations, cracks, voids, notches, etc.
These are causes for rejection unless suitable/satisfactory remedial action can be taken. Welding repairs to bevels are not permitted, without approval from the engineer/inspector. Inspectors needs report excessive or serious defects.
Plates subject to forming, rolling or dishing may require additional heat treatment and NDE to meet code requirements.
Third Party Inspection for Storage Tank- Shell Courses and Base Plates containing Welded Seams
This stage inspection is carried out when plates have been tacked using welding consumables and other parameters from an approved WPS.
Third party Inspector checks and report on:
- Cleanliness and fit up accuracy of weld preparation.
- Flatness of plates, methods of preventing distortion, e.g sequenced welding, strongbacks, backstep, etc.
- Application of preheat.
- Storage and handling of welding consumables.
- Interpass condition where welding is in progress.
- Cleaning of welds.
- Completion of test coupons, (where specified)
- NDE. Results need to meet specifications or code requirements.
- Hardness tests – when specified.
- Impact tests – when specified.
Weld repair may be permitted in accordance with the code requirements and is carried out only after investigation of the probable cause and in accordance with approved WPS documents.
All weld repairs need to be reported to the client by third party inspector.
Third Party Inspection for Storage Tank Post Weld Heat Treatment of Hot Formed Components
Third party Inspector carries out dimensional check and reviews furnace record chart to ensure heat treatment was carried out as specified.
Hardness measurement may be used to establish condition of material, heat affected zone or welds, as may be specified. Then the inspector checks dimensions, curvature, etc., after PWHT.
Third Party Inspection for Storage Tank – Assembly Inspection
Storage tanks may sometimes be assembled prior to despatch, this is witnessed and the results of any filling test recorded.
The number and thickness of the plates are checked if no trial assembly has been possible. Plates with access holes, manways and valve openings are visually and dimensionally checked.
Match marks, identification marks are checked to the drawing requirement. Name plates if attached need to be in accordance with the approved drawing.
Third Party Inspection for Storage Tank Painting and Coating
Surface preparation for painting is checked for the following points, according to specification by third party inspector:
- Cleaning method (commercial blast cleaning, near-white metal blast cleaning, etc. )
- Surface Preparation Level
- Freedom from weld spatter, blow-holes and other defects
- Dry film thickness is checked according to specification
Surface condition need to be free from pin-holes, runs damage and other discontinuity
Third Party Inspection for Storage Tank Spares and Accessories:
The third party inspector controls spares, tools and accessories and make visual and dimensional inspection for materials, workmanship and quantity according to purchase order specification and packing list.
Marking and/or Tag need to be checked for identification.
Third Party Inspection for Storage Tank- Reporting:
Third party inspector provides Inspection Visit Report (IVR) after each visit as well as a final report summarising the activities carried out during the storage tank production in accordance with the contract requirements and circulated within the time limits specified in the contract.
The report is in the format required by the client and clearly indicates final acceptance or rejection of the Storage Tank.
Third Party Inspection for Storage Tank Packing, Marking and Shipping:
The following points are checked by the third party inspector:
- Cleanliness and dryness of storage tank
- Rust prevention for all machined surfaces
- Protection for cover for all opening and protruding parts
- Spacing of plates
- Security from warping/transit damage
- Packing style and suitably for overseas transportation
- Shipping marks and other markings and notificationof welding prohibited, etc.
Third Party Inspection for Storage Tank – Fabrication Shop Documents
The following final documents are reviewed and signed off by third party inspector to the contract or purchase order requirement.
These may apply to both shop and site operations.
Component detail drawings, Manufacturer’s data reports, Material certificate or certified mill test reports, Material list or map, Welder record for each seam, Heat treatment records (Temperature-time record chart during PWHT), Dimensional record, NDE records, Hardness test record, Packing list, Spare parts and tool list.
Third Party Inspection for Storage Tank – Site Erection
The site third party inspector is responsible for all site operations up to and including final testing and certification of storage tanks.
Many operations are identical in nature to those already described for materials and fabrication inspection in the shops.
However, other factors which are likely to be more pertinent, include the necessity to closely watch for satisfactory climatic conditions and metal temperatures during welding and careful storage and handling of materials.
Site third party inspector carefully monitors Job site records of welders’ qualifications, approved weld procedures and site storage and handling of welding consumables.
The site third party inspector cross-checks all incoming plate, fabrications and material against certification. He ensures all material is clearly identified and during construction monitors transfer of markings, which is made to ensure all material of the completed tank is identifiable by such markings.
In the case of thin plates, marking need to be applied by painting or etching. All material need to be inspected prior to incorporation in the tank to ensure correct dimensions and freedom from unacceptable flaws, especially in edge preparations.
The inspector ensures that only approved procedures are used and that all welders and operators are suitably qualified. All welds are clearly identified with welder’s stamp or paint marking, as directed by the specification.
All welds need to be made to approved WPS and be inspected for conformity to finish profile.
Extent of NDE and all NDE requirements are monitored. Radiographs are reviewed and signed off by site third party inspector when they are satisfactory.
All defects requiring repair, are logged and reported and the inspector ensures that only approved weld procedures are utilised.
The inspector ensures that any required offsets or staggering of welds is correctly incorporated to code or project requirements. All fittings and fabrication are checked for conformity to tank curvature, prior to attachment. Major dimensional checks are witnessed to ensure compliance within specified tolerances of diameters, heights, circularity etc.
Third Party Inspection for Storage Tank – Site Erection Test
All pre-test procedures are monitored by third party inspector, including crack detection where required.
Hydrostatic and pneumatic tests are observed and reported, including vacuum box testing.
Third Party Inspection for Storage Tank – Site Erection Documentation
On completion of all aspects of tank construction and testing, the entire quality verification and construction documentation package are reviewed for accuracy and completeness prior to making a report of acceptance in accordance with the contract or purchase order requirement.
Third Party Inspection for Storage Tank Site Erection – Final Certification
Certification of completed tanks for compliance to code and specification requirements are prepared and countersigned by the site third party inspector prior to distribution, in accordance with project requirements.
Third Party Inspection for Storage Tank – Reporting:
Third party inspector provides Inspection Visit Report (IVR) after each visit as well as a final report summarising the activities carried out during the storage tank production in accordance with the contract requirements and circulated within the time limits specified in the contract.
The report is in the format required by the client and clearly indicates final acceptance or rejection of the storage tank.
Third Party Inspection for Storage Tank – Release Note:
When required by the contract or purchase order a release note is issued by third party inspection agency and given to the manufacturer when the Storage Tank have been finally accepted.
Return to Third Party Inspection or Storage Tank Inspection
Executive Summary & Industrial Inspection Scope
In demanding industrial environments across Oil, Gas, Petrochemical, Offshore, and Heavy Process Infrastructure, rigorous compliance with ISO 17020, API Source Inspector, ASME is essential to ensure operational integrity, personnel safety, and compliance with statutory regulatory frameworks. This technical specification provides QA/QC managers, procurement engineers, welding inspectors, and third-party inspection (TPI) agencies with an authoritative, field-tested guideline for “Third Party Inspection For Storage Tank”.
Ensuring compliance regarding third party inspection for storage tank services minimizes the risk of catastrophic asset failures, costly unscheduled shutdowns, and supplier non-conformances. The following technical sections delineate the scope of inspection, mandatory verification protocols, acceptance criteria, documentation deliverables, and root cause mitigation strategies.
Governing International Engineering Codes & Specifications
Verification and validation of Third Party Inspection For Storage Tank must strictly conform to the latest editions of the following international engineering codes and project specifications:
• **Primary Standard Reference:** ISO 17020, API Source Inspector, ASME
• **Quality Management & Inspection Systems:** ISO 9001:2015 & ISO/IEC 17020 (Requirements for the operation of various types of bodies performing inspection)
• **Material Compliance & Traceability:** EN 10204 Type 3.1 / 3.2 Inspection Certificates for metallic and non-metallic pressure-retaining components
• **Personnel Qualification:** ASNT SNT-TC-1A / ISO 9712 for NDT personnel, CSWIP 3.1 / AWS CWI for welding inspection, and NACE / AMPP Level 2/3 for coating and corrosion personnel
• **Statutory & Health Safety Directives:** ASME Boiler & Pressure Vessel Code (BPVC), API Standards, OSHA, and regional local authority regulations.
Step-by-Step Quality Control & Inspection Procedure
The execution of quality surveillance for Third Party Inspection For Storage Tank is structured across four progressive QA/QC intervention phases:
Stage 1: Pre-Inspection & Engineering Document Review (Review Point – R)
Prior to commencement of any physical activities or manufacturing operations related to Third Party Inspection For Storage Tank, the contractor or vendor must submit all technical submittals to the Owner or TPI agency for formal review and approval.
- Verification of approved Inspection and Test Plan (ITP) identifying all Hold (H), Witness (W), Review (R), and Surveillance (S) intervention points.
- Cross-examination of Material Test Reports (MTR / Mill Certificates) against standard design specifications (ISO 17020, API Source Inspector, ASME).
- Review and approval of specific Procedure Qualification Records (PQR), Welding Procedure Specifications (WPS), or calibration certificates.
- Verification that all measurement instruments, gauges, and NDT equipment hold valid calibration certificates from ISO/IEC 17025 accredited calibration laboratories (within 6 to 12 months validity).
Stage 2: In-Process Witnessing & Fabrication Control (Witness / Hold Point – W/H)
During the active execution phase, the certified inspector performs physical surveillance to ensure strict adherence to certified drawings, manufacturing procedures, and code tolerances.
- Verification of material traceability (heat number, heat treatment lot, plate number) transferred accurately onto fabricated components.
- Dimensional verification and visual inspection using calibrated gauges, micrometer depth dials, or laser alignment systems.
- Monitoring ambient environmental parameters (relative humidity, dew point, substrate temperature) when applying surface treatments, welding preheat, or pressure testing.
- Witnessing non-destructive examination (RT, UT, MT, PT, PMI) at specified percentages according to project critical rating and code requirements.
Stage 3: Final Acceptance, Pressure/Performance Testing & Marking (Hold Point – H)
The culminating milestone where the fully assembled or completed item is subjected to definitive acceptance tests in the presence of the Owner’s Third-Party Inspector (TPI).
- Execution of pressure proof tests (Hydrostatic at 1.3x to 1.5x MAWP or Pneumatic test) with dual calibrated pressure gauges and temperature recorders.
- Full visual inspection of completed surfaces, welds, protective coatings, and flange contact faces for absence of mechanical damage or code defects.
- Validation of permanent stamping, low-stress die markings, nameplate data verification, and barcoding in strict conformity with project specs.
- Clearing all open punch-list items, non-conformance reports (NCRs), and concession requests prior to issuance of the release note.
Stage 4: Packing, Preservation & Inspection Release (Inspection Release Certificate – IRC)
Ensuring the inspected equipment is adequately protected against atmospheric corrosion, mechanical shock, and marine transit degradation.
- Inspection of rust preventative coatings, desiccant bags, flange face blind protectors, and vapor corrosion inhibitor (VCI) packaging.
- Verification of heavy-lift sea fastening lugs, center-of-gravity markings, and export crating compliance (ISPM 15 wooden crating).
- Compilation and signing of the final Inspection Release Certificate (IRC / Shipping Release) and manufacturer data dossier (MDR).
Technical Acceptance Criteria & Tolerances Matrix
All measurements and physical characteristics must comply with the engineering tolerances and acceptance thresholds tabulated below:
| Inspection Parameter / Test Item | Applicable Standard & Clause | Permissible Tolerance / Acceptance Limit | Verification Method | Intervention Type |
|---|---|---|---|---|
| Material Chemical & Mechanical Verification | ISO 17020, API Source Inspector, ASME / EN 10204 3.1 | 100% compliance with minimum tensile, yield, elongation, and impact values (Charpy V-Notch at design temp) | Optical Emission Spectrometry (OES) / MTR Verification | Review (R) |
| Visual & Dimensional Tolerances | ISO 17020, API Source Inspector, ASME / Project Specs | Zero cracks, lack of fusion, severe pitting; dimensional tolerances within ±1.0mm to ±3.0mm per code drawings | Calibrated Vernier, Bridge Cam, Depth Micrometer | Witness (W) |
| Non-Destructive Examination (NDT) | ASME Sec V / ASNT SNT-TC-1A | 100% compliant with code acceptance criteria; zero planar defects or unpermitted volumetric indications | Radiographic (RT) / Ultrasonic (UT) / Magnetic Particle (MT) | Hold (H) |
| Pressure / Proof Testing (Hydrostatic) | ISO 17020, API Source Inspector, ASME / ASME Sec VIII | Test pressure maintained for minimum 30 to 60 mins; zero pressure drop, zero leakage or visible sweating | Dual calibrated Bourdon pressure gauges + Chart Recorder | Hold (H) |
| Surface Prep & Protective Coating Quality | SSPC-SP / NACE / ISO 8501 | Surface profile 50 – 75 µm; Dry Film Thickness (DFT) within 80/20 rule of specified nominal thickness | Replica Tape (ASTM D4417) & Magnetic Gauge (SSPC-PA 2) | Witness (W) |
| Nameplate & Final Preservation Verification | API / ASME / Client Specs | 316L SS nameplate securely affixed with correct design code, MAWP, design temp, and national board stamping | Physical visual check & VCI preservation verification | Hold (H) |
Mandatory QA/QC Dossier & Inspection Deliverables
Prior to the final issuance of the Inspection Release Certificate (IRC), the contractor and vendor must compile and submit the verified manufacturer data record containing:
- Approved Inspection & Test Plan (ITP) with sign-off stamps by Contractor, Client, and TPI.
- Material Test Reports (MTR / Mill Test Certificates EN 10204 Type 3.1 or 3.2).
- Certified Welding Procedure Specifications (WPS), Procedure Qualification Records (PQR), and Welder Performance Qualifications (WPQ).
- Calibration Certificates for all test instruments and measuring equipment (NABL / ISO 17025 accredited).
- Non-Destructive Examination Reports (RT, UT, MT, PT, PMI, Ferrite Content) evaluated by Level II/III inspectors.
- Heat Treatment & PWHT Time-Temperature Recorder Charts with thermocouple layout drawings.
- Hydrostatic / Pneumatic Pressure Proof Test Certificate with calibrated chart recorder logs.
- Surface Preparation and Protective Coating Inspection Reports (Daily environmental log, blast profile, DFT summary).
- Non-Conformance Report (NCR) and Concession Disposition Closeout Log.
- Official Inspection Release Certificate (IRC / Shipping Release Note) permitting packing and dispatch.
Common Non-Conformances & Field Mitigation Strategies
Based on extensive third-party inspection field records in oil & gas projects, the following deviations require heightened surveillance:
Defect / Hazard: Material Grade Substitution & Lack of Heat Traceability
Root Cause: Uncontrolled workshop storage, missing color coding, or unverified supplier sub-tier procurement without EN 10204 3.1 documentation.
Preventative Action: Enforce strict 100% Positive Material Identification (PMI) prior to cutting, and mandatory material receiving inspection with physical stamping cross-referenced to original mill test certificates.
Defect / Hazard: Out-of-Tolerance Fit-Up & Alignment Mismatch
Root Cause: Poor thermal cutting, thermal distortion from excessive preheat, or inadequate jigging and tacking arrangements.
Preventative Action: Establish a mandatory Witness/Hold point at joint fit-up before root pass deposition. Use calibrated Hi-Lo gauges to verify bevel angle, root face, and root gap according to the qualified WPS.
Defect / Hazard: Premature Coating Delamination & Blistering Under Film
Root Cause: Excessive soluble salt contamination (>20 mg/m²) left on the substrate, blast cleaning below dew point (<3°C above dew point), or oil/moisture in the blasting compressor air line.
Preventative Action: Perform Blotter Test (ASTM D4285) daily on compressed air, enforce Bresle patch chloride testing, and apply primer within 4 hours of abrasive blasting before rust blooming initiates.
Defect / Hazard: Pressure Drop During Final Hydrostatic Proof Testing
Root Cause: Micro-leakage through temporary test flange gaskets, entrapped air pockets inside vessel high points, or inadequate temperature stabilization.
Preventative Action: Ensure thorough venting at all high-point vents until bubble-free fluid emerges, allow minimum 15-minute temperature stabilization between filling medium and ambient metal, and torque all blind flanges with calibrated torque wrenches.
Frequently Asked Questions (FAQ)
Q: What are the mandatory qualifications for inspectors verifying Third Party Inspection For Storage Tank?
A: Inspectors must hold recognized international certifications applicable to the discipline. For welding and fabrication: CSWIP 3.1/3.2, AWS CWI, or API 510/570 Source Inspector. For NDT: ISO 9712 or ASNT SNT-TC-1A Level II minimum. For coatings: NACE / AMPP Level 2 or FROSIO Level III. Additionally, the inspection agency must operate under an ISO/IEC 17020 accredited quality management system.
Q: How does PtroTek resolve non-conformances (NCRs) encountered during vendor surveillance?
A: When a deviation from certified drawings or ISO 17020, API Source Inspector, ASME is detected, the inspector issues a formal Non-Conformance Report (NCR) within 24 hours. The vendor must submit a Root Cause Analysis (RCA) and proposed disposition (Rework, Repair, or Concession). Work on the affected component is halted (Hold Point) until the Owner’s engineering authority approves the disposition and a re-inspection confirms full compliance.
Q: What is the difference between Witness (W) and Hold (H) points in an Inspection & Test Plan (ITP)?
A: A Hold Point (H) is a mandatory milestone where fabrication or testing CANNOT proceed without the physical presence of the designated client or third-party inspector. Written clearance or stamping is strictly required. A Witness Point (W) requires prior notification (typically 24 to 48 hours) to the inspector; however, if the inspector fails to attend at the scheduled time, fabrication or testing may proceed with subsequent review of the test records.
Q: Can international clients review inspection reports and photos in real time?
A: Yes. PtroTek provides comprehensive Flash Reports issued within 24 hours of inspection completion, followed by detailed formal inspection reports accompanied by high-resolution calibrated photographic evidence, dimension logs, and signed vendor test records for complete global transparency.